Dipl.-Ing. Thomas Duesberg
Angestellt, Project Manager, GfpA AG, Baden, Switzerland
Wuerenlos, Schweiz
Werdegang
Berufserfahrung von Thomas Duesberg
Bis heute 12 Jahre und 8 Monate, seit Okt. 2011
Project Manager
GfpA AG, Baden, Switzerland
I was working on the following sites: Swiss nuclear power plant in Muehleberg as project manager. Kusile STPP in South Africa as access-coordinator and supervisor. Presently working on various projects and sales support for electrical and DCS projects.
10 Jahre und 1 Monat, Aug. 2001 - Aug. 2011
Site Manager / Project Manager
ABB Mannheim, Germany
Site manager / Project manager on the following sites: Thermal Power Plant Krabi, Thailand ABB office in Cheonan, South Korea Combined cycle power plant in Benghazi, Libya STPP power plant in Benghazi, Libya Hydro electric power plant in Karakaya, Turkey CCPP in Sulaymaniah, Iraq
1 Jahr und 7 Monate, Jan. 2000 - Juli 2001
Assistant Project Manager
ABB Mannheim, Germany
Assistant of the project manager at the Tuas South Incineration Plant in Singapore
1 Jahr, Jan. 1999 - Dez. 1999
Maintenance and Service Engineer
ABB Mannheim, Germany
Assessment and upgrade of DCS systems provided by ABB in respect of the Y2K problems.
11 Jahre und 1 Monat, Jan. 1988 - Jan. 1999
Commissioning Engineer, Commissioning Manager
ABB Mannheim, Germany
Commissioning engineer / manager for DCS on the following sites: Natural Gas storage and transportation plants in various locations in Germany Refuse incineration plant in Cologne, Germany Refinery power plant in Leuna, Germany
Ausbildung von Thomas Duesberg
9 Jahre und 10 Monate, Aug. 1967 - Mai 1977
Ship operation engineering
Hochschule Bremerhaven
Sprachen
Englisch
-
Deutsch
-