Müller Behälterbau GmbH & Co. KGhat einen Beitrag geschrieben.2. November 2016
On October 26 the pressure test was carried out on the two reactors and the tanks were committed to the customer. The customer will carry out a number of test carried before commissioning to use the biogas to generate electricity for the paper plant. The erection time of the two reactors took 40 days. Thanks to all who contributed. Project data: Description: Biobed Reactor Quantity: two pieces Capacity: 840 m³ Weight: 24.300 kg allowable Pressure: - 5/+70 mbar Material: 1.43...